Phase 2 of construction includes the installation of the ultimate improvements at the intersection of Valpico Road and Corral Hollow Road including:
- Curb returns
- Wet utilities
- Permanent traffic signal
All improvements outside of the intersection along Corral Hollow Road are considered interim until the ultimate widening of Corral Hollow Road is constructed in Phase 4. Interim improvements include:
- Pavement widening north and south on Corral Hollow Road (approximately 1,000 feet)
- Transition from two-to-four lanes on Valpico Road, west of the intersection