Corral Hollow Corridor Construction Phases

City of Tracy at the intersection of Corral Hollow Road and Valpico Road.

Click here for the Construction Update Report!

The Eight Phases of Construction

Welcome to the City of Tracy Corral Hollow Corridor website! Here, you will find updates on roadway construction and improvement initiatives along Corral Hollow Road. This is a long-term, eight-phase program designed to increase mobility and improve connectivity for those traveling through our community for generations to come.

Proposed Timeline

Schedule subject to change.

Corral Hollow Road & Valpico Road — Temporary Traffic Signal Installation (Under Construction)

2022

2023

February 2022 – March 2022
Design
April 2022 – June 2022
Construction Bid Period
June 2022 – November 2022
Construction
September 2023 - October 2023
Modify Configuration
November 2022 - August 2023
Traffic Study
Corral Hollow Road & Valpico Road — Intersection Widening & Permanent Traffic Signal Installation

2022

2023

2024

August 2022 – March 2023
Design
September 2023 – November 2023
Construction Bid Period
March 2024 - November 2024
Tentative Construction Start Date
Corral Hollow Road & Linne Road — Intersection Widening, UPRR Crossing Improvements, and Traffic Signal Installation

2022

2023

2024

2025

October 2022 – October 2023
Design & Right of Way
November 2023 – January 2024
Tentative Construction Bid Period (Pending Railroad Crossing Upgrades by UPRR)
July 2024 - March 2025
Tentative Construction Start Date
Corral Hollow Road from Parkside Drive to Linne Road — Road Widening
Schedule Pending
Corral Hollow Road from Linne Road to the CA Aqueduct — Road Widening
Schedule Pending
Corral Hollow Road from CA Aqueduct to I-580 — Road Widening

2022

2023

January 2022 – May 2023
Tentative Construction Completion
I-580 & Corral Hollow Road — Roundabout and Interchange Improvements

2022

2023

2024

2025

2026

2027

October 2022 – March 2024
Project Approval & Environmental Document (PA&ED)
May 2023 – October 2024
Design
November 2024 – February 2025
Tentative Bid Period
July 2025 - September 2027
Tentative Construction Start Date
Sierra View Drive & Corral Hollow Road — Intersection Improvements

2023

March 2023 – December 2023
Tentative Construction Completion

What are the benefits
for our community?

Checkmark in shield

Improve Safety

two lane road with two cars

Alleviate Congestion

increasing bar shart with arrow

Improve Capacity

dual two lane roads

Increase Lanes / Shoulder Widths

Know Before You Go

Know before you go: Keep up-to-date on construction and detours so you can get to your destination safely, quicker, and stress-free. Click on each contruction phase fpr updates. Call 511. Check our social media.